X can do a piece of work in 6 days, while x and y boh can do the same piece of work in 3/2 days how long will y alone take to complete. 1- 2 days 2- 4 days 3- 9/2 days?
Most Upvoted Answer
X can do a piece of work in 6 days, while x and y boh can do the same ...
Understanding the Work Rates
To solve the problem, we first determine the work rates of X and the combined work of X and Y.
Work Rate of X
- X can complete the work in 6 days.
- Therefore, X's work rate is 1/6 of the work per day.
Work Rate of X and Y Together
- X and Y together can finish the work in 3/2 days.
- Their combined work rate is 1/(3/2) = 2/3 of the work per day.
Finding Y's Work Rate
- Let Y's work rate be represented as 1/Y (where Y is the number of days Y takes alone to complete the work).
- The equation for their combined work rates is:
(1/6) + (1/Y) = (2/3)
- Rearranging the equation gives:
1/Y = (2/3) - (1/6)
Calculating Y's Work Rate
- To combine the fractions, we find a common denominator (which is 6):
1/Y = (4/6) - (1/6) = (3/6) = 1/2
- Solving for Y gives Y = 2.
Conclusion
- Therefore, Y alone will take 2 days to complete the work.
In summary, the answer is:
Y will take 2 days to complete the work alone.
Explore Courses for SSC exam
X can do a piece of work in 6 days, while x and y boh can do the same piece of work in 3/2 days how long will y alone take to complete. 1- 2 days 2- 4 days 3- 9/2 days?
Question Description
X can do a piece of work in 6 days, while x and y boh can do the same piece of work in 3/2 days how long will y alone take to complete. 1- 2 days 2- 4 days 3- 9/2 days? for SSC 2024 is part of SSC preparation. The Question and answers have been prepared according to the SSC exam syllabus. Information about X can do a piece of work in 6 days, while x and y boh can do the same piece of work in 3/2 days how long will y alone take to complete. 1- 2 days 2- 4 days 3- 9/2 days? covers all topics & solutions for SSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for X can do a piece of work in 6 days, while x and y boh can do the same piece of work in 3/2 days how long will y alone take to complete. 1- 2 days 2- 4 days 3- 9/2 days?.
Solutions for X can do a piece of work in 6 days, while x and y boh can do the same piece of work in 3/2 days how long will y alone take to complete. 1- 2 days 2- 4 days 3- 9/2 days? in English & in Hindi are available as part of our courses for SSC. Download more important topics, notes, lectures and mock test series for SSC Exam by signing up for free.
Here you can find the meaning of X can do a piece of work in 6 days, while x and y boh can do the same piece of work in 3/2 days how long will y alone take to complete. 1- 2 days 2- 4 days 3- 9/2 days? defined & explained in the simplest way possible. Besides giving the explanation of X can do a piece of work in 6 days, while x and y boh can do the same piece of work in 3/2 days how long will y alone take to complete. 1- 2 days 2- 4 days 3- 9/2 days?, a detailed solution for X can do a piece of work in 6 days, while x and y boh can do the same piece of work in 3/2 days how long will y alone take to complete. 1- 2 days 2- 4 days 3- 9/2 days? has been provided alongside types of X can do a piece of work in 6 days, while x and y boh can do the same piece of work in 3/2 days how long will y alone take to complete. 1- 2 days 2- 4 days 3- 9/2 days? theory, EduRev gives you an ample number of questions to practice X can do a piece of work in 6 days, while x and y boh can do the same piece of work in 3/2 days how long will y alone take to complete. 1- 2 days 2- 4 days 3- 9/2 days? tests, examples and also practice SSC tests.
Explore Courses for SSC exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev