Quant Exam  >  Quant Questions  >  A works twice as fast as B. If B can complete... Start Learning for Free
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in
  • a)
    4 days
  • b)
    6 days
  • c)
    8 days
  • d)
    18 days
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
A works twice as fast as B. If B can complete a work in 12 days indepe...
Ratio of rates of working of A and B = 2 : 1
So, ratio of time taken = 1 : 2
B's 1 day's work = 1/12
∴ A's one day work = 1/3 (2 times of B's work)
(A + B)'s 1 day's work = (1/6) + (1/12) = 3/12 = 1/4
So, A and B together can finish work in 4 days.
View all questions of this test
Most Upvoted Answer
A works twice as fast as B. If B can complete a work in 12 days indepe...
Given: A works twice as fast as B. B can complete the work in 12 days.

To find: The number of days in which A and B can together finish the work.

Solution:

Let us assume that B can complete the work in 'x' days.

Then A can complete the same work in x/2 days. (As A works twice as fast as B)

Given that B can complete the work in 12 days.

Therefore, x = 12.

So, B completes the work in 12 days.

A can complete the same work in 12/2 = 6 days.

Now, let us consider the case where A and B work together.

Let the total work be denoted by 'W'.

Let us assume that A and B can together complete the work in 'd' days.

In one day, the work done by A and B together = (1/6 + 1/12) = 1/4. (As A can complete 1/6th of the work in a day and B can complete 1/12th of the work in a day)

Therefore, the work done by A and B together in 'd' days = d/4.

As per the question, the work done by A and B together is 'W'.

Therefore, we can write:

d/4 = W

d = 4W

Therefore, A and B can together complete the work in 4 days.

Hence, the correct option is (a) 4 days.
Free Test
Community Answer
A works twice as fast as B. If B can complete a work in 12 days indepe...
Ratio of rates of working of A and B = 2 : 1
So, ratio of time taken = 1 : 2
B's 1 day's work = 1/12
∴ A's one day work = 1/3 (2 times of B's work)
(A + B)'s 1 day's work = (1/6) + (1/12) = 3/12 = 1/4
So, A and B together can finish work in 4 days.
Explore Courses for Quant exam
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work ina)4 daysb)6 daysc)8 daysd)18 daysCorrect answer is option 'A'. Can you explain this answer?
Question Description
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work ina)4 daysb)6 daysc)8 daysd)18 daysCorrect answer is option 'A'. Can you explain this answer? for Quant 2025 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work ina)4 daysb)6 daysc)8 daysd)18 daysCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Quant 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work ina)4 daysb)6 daysc)8 daysd)18 daysCorrect answer is option 'A'. Can you explain this answer?.
Solutions for A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work ina)4 daysb)6 daysc)8 daysd)18 daysCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work ina)4 daysb)6 daysc)8 daysd)18 daysCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work ina)4 daysb)6 daysc)8 daysd)18 daysCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work ina)4 daysb)6 daysc)8 daysd)18 daysCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work ina)4 daysb)6 daysc)8 daysd)18 daysCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work ina)4 daysb)6 daysc)8 daysd)18 daysCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev