For the given project network, where numbers along various activities represent normal time.
Find the project completion expected duration (Te)?
  • a)
    28
  • b)
    16
  • c)
    30
  • d)
    32
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
For the given project network, where numbers along various activities ...
Critical path is 1-2-3-4-5-5
And expected duration is 32 days.
View all questions of this test
Explore Courses for GATE exam
For the given project network, where numbers along various activities represent normal time.Find the project completion expected duration (Te)?a)28b)16c)30d)32Correct answer is option 'D'. Can you explain this answer?
Question Description
For the given project network, where numbers along various activities represent normal time.Find the project completion expected duration (Te)?a)28b)16c)30d)32Correct answer is option 'D'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about For the given project network, where numbers along various activities represent normal time.Find the project completion expected duration (Te)?a)28b)16c)30d)32Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for For the given project network, where numbers along various activities represent normal time.Find the project completion expected duration (Te)?a)28b)16c)30d)32Correct answer is option 'D'. Can you explain this answer?.
Solutions for For the given project network, where numbers along various activities represent normal time.Find the project completion expected duration (Te)?a)28b)16c)30d)32Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of For the given project network, where numbers along various activities represent normal time.Find the project completion expected duration (Te)?a)28b)16c)30d)32Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of For the given project network, where numbers along various activities represent normal time.Find the project completion expected duration (Te)?a)28b)16c)30d)32Correct answer is option 'D'. Can you explain this answer?, a detailed solution for For the given project network, where numbers along various activities represent normal time.Find the project completion expected duration (Te)?a)28b)16c)30d)32Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of For the given project network, where numbers along various activities represent normal time.Find the project completion expected duration (Te)?a)28b)16c)30d)32Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice For the given project network, where numbers along various activities represent normal time.Find the project completion expected duration (Te)?a)28b)16c)30d)32Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice GATE tests.
Explore Courses for GATE exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev